Evie’s Beam and Building Dreams – Latest Construction Progress

Exciting progress continues on our New Building project. The damp proof membrane and insulation have now been fully installed on the ground floor, preparing the way for floor screeding, which is scheduled to begin imminently.

Construction of the first-floor walls is well advanced and expected to be completed by today or Monday. Once this stage is finished, the steelwork will be installed to support the second-floor cassettes – another important milestone in the build.

A particularly proud moment this week involved a steel beam signed and dated by one of our students, Evie. The beam was fabricated by a local company where Evie’s father works.  He brought her to the workshop so she could take part in this meaningful step and leave a lasting mark on the new school building.

We look forward to sharing more exciting updates as the project progresses!