🪜🏫 Stairs, Ceilings & Canopies – The Transformation Continues!

✔ What’s been completed this week

  • Vinyl flooring has been installed on Stair 1 across all floors.
  • Stair 2 is now fully prepared to start, and the main entrance lobby is ready for the upcoming reception-desk installation.
  • All ceiling grids have now been installed in all rooms. In particular, Ground-floor Classroom 1 (the sample room) has had its ceiling panels fitted.
  • The canopy roof is now installed, cladded, and fitted with gutters & downpipes.
  • Site fencing on the west elevation has been removed to allow for groundworks and later tarmac laying.
  • Groundworkers have removed excess material from the site.  
  • Mechanical, electrical and decoration works are progressing across all floors.

🔜 What’s next / What to watch

  • Commence installation of flooring on Stair 2 and the main entrance lobby works ahead of the reception desk fit-out.
  • Groundworks and tarmac laying on the west elevation now that site fencing has been cleared.
  • Begin installation of the reception-desk infrastructure (power/databases) in the lobby.
  • Continue mechanical, electrical and decoration across all areas to move closer to handover readiness.

💡 Spotlight of the week

The removal of the west-elevation fencing and start of external foundations work is a key turning point – from “building in progress” to “this will soon be part of our daily school life”. You can almost imagine students passing through the new entrance.