🚧 Progress in Motion: The Build Takes Shape – Let’s “Fifteen to Finish” This Together! 🏗️✨

Significant progress has been made across multiple areas of the site. The roof cassettes and parapet walls are now approximately 60% complete, with installation of the remaining Second Floor walls currently underway to allow the continuation of roof works. The mechanical and electrical installation continues, marking the beginning of vital services integration. Electrical containment is being installed with gas and water pipework following closely behind.

Ceiling boarding is now complete on the Ground Floor and is progressing well on the First Floor. Staircase 1 has been fully installed up to roof level, and the installation of Staircase 2 is now underway, enhancing internal access across the building.

Baxall is continuing to drive the build forward with precision and energy. With the shape and structure rapidly emerging, each milestone brings us closer to a finished building we can all be proud of – exciting times lie ahead.

The building is well underway, but we haven’t finished fundraising and we really need your help to close the gap. 

Find out more here:

Https://mggs.ptly.uk/donatenow

This project is more than just bricks, it’s a great opportunity to preserve our past and invest in our future.