The Helen Keen Building Nears the Finish Line – Exciting Progress Inside and Out!

Excitement continues to build on site as we edge closer to completion! Here’s what’s been happening this week:

Big Highlights

🔬 Science Labs Taking Shape – The installation of Science Lab furniture is progressing brilliantly, with three labs now fully complete. The spaces are really starting to look the part!

🎶 Music Rooms Ready to Perform – The acoustic flooring is now complete, bringing us one step closer to creating inspiring, soundproof learning spaces.

🏗️ The Helen Keen Name Revealed Soon! – Brickwork to the West Elevation is complete, and scaffold striking has commenced – keep your eyes peeled as the building name will soon be proudly on display!

Site Progress

🚧 Groundworks Back in Action – Groundworkers have recommenced on site to finish drainage and start forming pathways around the back of the building.

🛗 Lift Installed – Another major milestone reached with the lift now fully installed and operational.

The Helen Keen Building continues to take shape both inside and out.  Every week is revealing more of the exciting new facilities that will be ready to welcome students and staff in January 2026 (fingers crossed!)