🔌🏫 Helen Keen Building – Start of Term Update 🚧

The new term kicks off with great momentum on site as we move closer to completion!

  • Electrical installation is progressing well, with a target to get power on next week ⚡
  • The front canopy installation is now complete, with finishing touches starting next week
  • Vinyl flooring is being laid to the final classrooms and staircases, bringing interiors together
  • Sanitaryware installation is underway in the toilets
  • The plant room fit-out continues at pace
  • Drainage works remain ongoing around the building
  • Pathways are now being formed to the perimeter, giving a real sense of the final layout
  • Ceiling grid installation continues internally

Each week brings us another step closer to seeing the Helen Keen Building fully come to life – the finish line is in sight! 🎉